| Construction of 2 Storey visitor centre
comprising of a tea room, lecture room, information
area, kitchen, stores and toilet to ground floor. This
development will include car park facilities, lecture
facilities for 150 seats, gallery balcony area and
restaurant. Reinforced concrete foundations with
reinforced concrete slab. Reinforced concrete columns,
reinforced concrete stair walls and lift. Precast
concrete stepped auditorium slab units. Cavity wall
construction comprising block work inner and outer leaf
in parts in addition to brick outer leaf in parts. Flat
built up roof system with specialist curved ceiling to
first floor roof. Natural stone, marmoleum, tiled and
woodblock floor finishes.
| Client |
Office of Public Works |
| Building Type |
Tourism & Leisure |
| Value |
€4.3 m |
| Architect |
Office of Public Works |
| Engineer |
John B. Barry & Partners Limited |
| Quantity Surveyor |
Bruce Shaw Partnership |
| |
|
|
|
|
|